Study on Amended Ecodesign Working Plan
under the Ecodesign Directive

(remaining energy-using and new energy-related products)

Project planning

The study has started late October 2010 and was finalised in December 2012. The table below gives the original indicative timeline for the tasks.

 

Date (indicative)

Description Task/Result

Nov 2010

Project start
Launch website www.ecodesign-wp2.eu

Feb 2011

Draft report Task 1-2
preliminary results Task 3

Mar 2011

1st stakeholder meeting 11 Mar 2011

Apr 2011

Stakeholder consultation

May 2011

Draft report Task 1-3

Jun 2011

 

Jul 2011

Draft final report Task 1-4

Aug 2011

 

Sep 2011

2nd Stakeholder meeting 16 Sep 2011

Oct 2011

Final report Task 1-4


 